Bill of Quantities - Contingency Sum

Contingency Sum

A Contingency sum is an item found within a Bill of quantities (BoQ).

The item refers to unforeseeable cost likely to be incurred during the contract.

There are two types of contingency sum. The first refers to a specific item i.e. 'additional alterations to services when installing said shower unit'; where an item for alterations to existing services is not contained within the BoQ but some work is envisaged.

The second type of sum is where money can be allocated to any item, within the BoQ, in the same way as the above example or used as 'additional work to be undertaken by the contractor, at the request of the contract administrator'.

The first is usually approximated by the client’s PQS and the second by the contractors QS (or commercial manager).

Additional requirements is referred as Bill of materials (BOM).

Read more about this topic:  Bill Of Quantities

Famous quotes containing the words sum and/or contingency:

    We didn’t come to dig in Egypt for medals. Much more is learned from studying bits of broken pottery than from all the sensational finds. Our job is to increase the sum of human knowledge of the past, not to satisfy our own curiosity.
    John L. Balderston (1899–1954)

    Life, as the most ancient of all metaphors insists, is a journey; and the travel book, in its deceptive simulation of the journey’s fits and starts, rehearses life’s own fragmentation. More even than the novel, it embraces the contingency of things.
    Jonathan Raban (b. 1942)